SAP Activate Project Manager-Certification Questions and Answers( Sample)

Hello There, If you are preparing for SAP Activate Project Manager Certification. then I have good news for you!

Somehow, I have collected little information on the certification Syllabus and most likely asked certification questions.

Certification Title: SAP Certified Associate – SAP Activate Project Manager

Exam Code: C_ACTIVATE13

Level: Associate

Duration: 180 Minutes

Number of Questions: 80

passing score: C_ACTIVATE13 – 65% , C_ACTIVATE12 – 61%

Reference Books: ACT100 and  ACT200  ACT200  (SEE COURSE DETAIL FROM SAP)

Topic Areas

Please see below the list of topics that may be covered within this certification and the courses that cover them.

Description

  • The “SAP Certified Associate – SAP Activate Project Manager” certification exam verifies that the candidate has the knowledge required in the area of SAP project management. This certificate builds on basic consultant skills and experience that is then refined by practical experience during several projects. This exam validates whether SAP focused project managers have advanced business skills and the ability to apply methodologies and tools. Aside from advanced communication and presentation skills, this certificate also verifies that the project manager has skills to manage internal and external stakeholders, basic knowledge of change management processes, and communicating these processes to others. This exam validates that project manager can successfully manage the end-to-end transition of the project from Sales to Realization, can develop roadmaps for project execution, and understand testing and quality management. In particular for SAP related projects, the exam verifies that the Project Manager can apply the SAP Activate Methodology.

Topic Areas

Please see below the list of topics that may be covered within this certification and the courses that cover them. Its accuracy does not constitute a legitimate claim; SAP reserves the right to update the exam content (topics, items, weighting) at any time.

Please refer below the SAP link for the latest update

https://training.sap.com/certification/c_activate12-sap-certified-associate—sap-activate-project-manager-g/

Agile Delivery Approach> 12%

Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects.

Workstreams Overview> 12%

Describe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology

Agile Project Planning8% – 12%

Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog

Transition Path “New Implementation SAP S/4HANA Cloud”8% – 12%

Describe concepts, landscape overview, and specifics in Workstreams related to implementing  SAP S/4HANA Cloud.

SAP Activate Elements8% – 12%

Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework. Include Fit to Standard

SAP Activate Overview8% – 12%

Define factors influencing SAP Activate, its purpose and place among other frameworks

Transition Path “New Implementation SAP S/4HANA Cloud, Single Tenant Edition”< 8%

Describe concepts, landscape overview and specifics in Workstreams related to implementing S/4HANA Cloud, Single Tenant Edition.

Transition Path “System Conversion”< 8%

Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path.

Transition Path “Selective Data Transition”< 8%

Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path.

Transition Path “New Implementation SAP S/4HANA”< 8%

Describe concepts, landscape overview and specifics in Workstreams related to implementing S/4HANA.

General Information

Exam Preparation (Disclaimer- From SAP- Read more from Below Link)

IMPORTANT: All SAP consultant certifications are now available as Cloud Certifications in the Certification Hub and can be booked with product code CER006. With CER006 – SAP Certification in the Cloud, you can take up to six exams attempts of your choice in one year – from wherever and whenever it suits you!  Test dates can be chosen and booked individually.

Those of you who prefer to get certified on-site at an SAP training center instead can still do so. Official dates for the certification tests are listed on the right.

Please check this for more details in SAP Training Portal.

SAP Activate Project Manager Sample Questions:

from ERPREP.com

01. What can you do in the SAP Roadmap Viewer tool?
Please choose the correct answer.
a) Create a customer-specific version of a roadmap.
b) Navigate detailed Solution Implementation Roadmaps.
c) Download full roadmap content for offline navigation.
d) Comment on Deliverables and Tasks within Roadmaps.
02. How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
a) Register on SAP Service Marketplace
b) Send e-mail to SAP contact address
c) Submit e-mail address via on-line form
d) Join SAP S/4HANA group on SAP Community Network
03. Where can you find Project Library Accelerators?
Please choose the correct answer.
a) SAP Best Practices Explorer
b) SAP Cloud Appliance Library
c) Fully Activated Appliance
d) SAP Roadmap Viewer
04. What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
a) Daily status meeting with project manager
b) Daily team stand-up meeting
c) Daily e-mail status updates to project manager
d) Daily progress review meeting with sponsor
05. What are the three elements of SAP Activate?
There are 3 correct answers to this question.
a) Content
b) Methodology
c) Focused Build
d) Tools
e) SAP Solution Manager
06. What is the minimum number of Quality Gates mandated for SAP S/4HANA transition projects?
Please choose the correct answer.
a) 2
b) 3
c) 4
d) 5
07. Which activities are critical for delivering Agile projects?
There are 2 correct answers to this question.
a) Retrospective agenda creation
b) Sprint planning
c) Release planning
d) Blueprint scheduling
08. In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
a) Prepare
b) Explore
c) Realize
d) Deploy
09. Who determines the priority of user stories in the backlog of an Agile project?
Please choose the correct answer.
a) Project Manager
b) Project Team
c) SCRUM Master
d) Product Owner
10. What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
a) Plan -> Design -> Build -> Operate
b) Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
c) Plan -> Build -> Run -> Sustain
d) Prepare -> Discover -> Explore -> Realize -> Deploy -> Run

Answers

1-b, 2-c,3-d,4-b,5-a,b,d,6-c,7-b,c,8-d,9-d,10-b